Willey
Named in 4 PJM planning documents for 2 projects, from May 15, 2026 to October 6, 2026.
Existingdescribed as
DEOKzone
138 kVkV as printed
4mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Customer Load Request DEOK-2025-003 |
Not printed | Not printed | Not printed | 800 MW | 2026-09-08 TEAC |
| Mt. Healthy Substation Rebuild DEOK-2026-002 · s3910.1 - .3 |
Engineering | $8.6M | 05/07/2029 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | BECKETT; COTTON RUN; MIAMI FORT; MILLIKIN; PORT UNION; TODHUNTER; WAYNE MADISON; WEST MILTON; WOODSDALE → BECKETT; COTTON RUN; MIAMI FORT; MILLIKIN; MORGAN; PORT UNION; TODHUNTER; WAYNE MADISON; WEST MILTON; WILLEY; WOODSDALE | 2025-07-08 | 2026-09-08 |
| Status | conceptual (Scoping) → engineering (Engineering) | 2026-05-15 | 2026-10-06 |
| Substations named | FINNEYTOWN; MAPLEKNOLL; MT HEALTHY; TERMINAL; WILLEY → FINNEYTOWN; MAPLEKNOLL; MT HEALTHY; WILLEY | 2026-10-06 | Not reported |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - DEOK Local Plan Submission of the supplemental projects for 2026 p. 9 |
Mt. Healthy Substation Rebuild | No role wording |
| 2026-09-30* | SRRTEP Western DEOK local plan submission of the supplemental projects for 2026 RTEP p. 9 |
Mt. Healthy Substation Rebuild | No role wording |
| 2026-09-08 | TEAC Item 08 - DEOK Supplemental Projects p. 9 |
Customer Load Request | “Miami Fort and Willey 138 kV substations” 138 kV |
| 2026-05-15 | SRRTEP Western Item 06 - DEOK Supplemental Projects p. 4 |
Mt. Healthy Substation Rebuild | No role wording |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.