Substation Scout

Cookstown

Named in 9 PJM planning documents for 10 projects, from October 8, 2024 to July 7, 2026.

Existingdescribed as
JCPLzone
230 kV, 230-34.5 kV, 34.5 kVkV as printed
12mentions

Also printed as: Cookstown Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Great Adventure 34.5 kV Substation
b4017.2
Not printed $61.68 M 6/1/2030 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Great Adventure 34.5 kV Substation Not printed $61.68 M 6/1/2030 Not printed 2025-10-16
SRRTEP Mid-Atlantic
Cookstown – Larrabee – Whitings 230 kV Line
JCPL-2022-005 · s3298.1, s3298.2, s3298.3, s3298.4, s3298.5
Not printed $50.4M 12/1/2024 Not printed 2024-10-08
TEAC
Cookstown Substation
JCPL-2023-010 · s3414.1
Not printed $ 7.95 M 1/31/2024 Not printed 2024-10-08
TEAC
Automatic Restoration Projects
JCPL-2023-027 · s3403.1
Not printed $ 0.64 M 12/31/2024 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Manchester 230-34.5 kV Substation
JCPL-2026-001
Not printed Not printed Not printed 23 MW 2026-01-06
TEAC
McGuire 34.5 kV Substation, NJ
JCPL-2026-007
Not printed Not printed Not printed 30 MW 2026-03-18
SRRTEP Mid-Atlantic
Cookstown Substation, NJ
JCPL-2026-019
Not printed Not printed Not printed Not printed 2026-05-14
SRRTEP Mid-Atlantic
Cookstown- Windsor 34.5 kV H60 Line, NJ
JCPL-2026-021
Not printed Not printed Not printed Not printed 2026-06-16
SRRTEP Mid-Atlantic
Lakewood, NJ
JCPL-2026-026
Conceptual $292.4M 12/31/2032 Not printed 2026-07-07
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named COOKSTOWN; LARRABEE; WHITINGS → COOKSTOWN; LARRABEE; MANCHESTER; WHITINGS 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 59
Cookstown – Larrabee – Whitings 230 kV Line “Expand Cookstown Substation from a four-breaker ring bus”
230 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 83
Automatic Restoration Projects No role wording
34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 93
Cookstown Substation “Replace the 230-34.5 kV No. 2 Transformer at Cookstown”
230-34.5 kV
2026-07-07 TEAC
Item 07 - JCPL Supplemental Projects p. 9
Lakewood, NJ No role wording
230 kV
2026-06-16 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 6
Cookstown- Windsor 34.5 kV H60 Line, NJ No role wording
34.5 kV
2026-05-14 SRRTEP Mid-Atlantic
Item 05 - JCPL Supplemental Projects p. 11
Cookstown Substation, NJ “existing Cookstown Substation 34.5 kV oil circuit breakers”
34.5 kV
2026-03-18 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 4
McGuire 34.5 kV Substation, NJ No role wording
34.5 kV
2026-01-06 TEAC
Item 03 - JCPL Supplemental Projects p. 3
Manchester 230-34.5 kV Substation No role wording
230 kV
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 29
Great Adventure 34.5 kV Substation “At Cookstown Substation, replace 34.5 kV breaker, two disconnect switches, relaying and ancillary terminal equipment”
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 29
Great Adventure 34.5 kV Substation “At Cookstown Substation, replace 34.5 kV breaker”
34.5 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 59
Cookstown – Larrabee – Whitings 230 kV Line “Expand Cookstown Substation from a four-breaker ring bus to a five-breaker ring bus”
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 93
Cookstown Substation “Replace the 230-34.5 kV No. 2 Transformer at Cookstown with a 168 MVA unit.”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this