Pine

Named in 5 PJM planning documents for 4 projects, from September 19, 2025 to June 17, 2026.

Not stateddescribed as
ATSIzone
138 kV, 69 kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Tusc Substation
ATSI-2023-011
Conceptual $16.72M 12/31/2027 Not printed 2025-09-19
SRRTEP Western
Bulk Mail Facility 138 kV
ATSI-2026-002
Conceptual $1.69M 12/31/2027 Not printed 2026-05-15
SRRTEP Western
Cranberry - Pine No.1 138kV Line
ATSI-2026-017
Not printed Not printed Not printed 28 MW 2026-02-13
SRRTEP Western
The Ingomar (Pine) 69 kV Rebuild
ATSI-2026-045
Not printed Not printed Not printed Not printed 2026-06-17
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named FIRESTONE; PINE; SOUTH AKRON; STAR; TUSC; URBAN; WADSWORTH; WEST AKRON → TUSC 2025-09-19 2026-10-06
Substations named BULK MAIL FACILITY; FERNWAY TAP; PINE → BULK MAIL FACILITY; FERNWAY; FERNWAY TAP; PINE 2026-01-16 2026-05-15
Substations named BULK MAIL FACILITY; FERNWAY; FERNWAY TAP; PINE → BULK MAIL FACILITY 2026-05-15 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 02 - ATSI Supplemental Projects p. 5
The Ingomar (Pine) 69 kV Rebuild No role wording
69 kV
2026-05-15 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 10
Bulk Mail Facility 138 kV No role wording
138 kV
2026-02-13 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 5
Cranberry - Pine No.1 138kV Line No role wording
138 kV
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 4
Bulk Mail Facility 138 kV No role wording
138 kV
2025-09-19 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 8
Tusc Substation No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.