Muskingum River
Named in 3 PJM planning documents for 3 projects, from May 15, 2026 to October 6, 2026.
Existingdescribed as
AEPzone
138kV, 345 kVkV as printed
4mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Muskingum River, OH AEP-2025-OH013 · s4024.1-2 |
Conceptual | $5.782 M | 12/06/2027 | 200MW | 2026-10-06 TEAC |
| Muskingum River 345kV Customer Delivery AEP-2025-OH015 |
Conceptual | $20.574 M | 11/01/2028 | 1200MW | 2026-10-06 TEAC |
| Muskingum River - Kammer 345 kV Line Section AEP-2026-OH041 |
Not printed | Not printed | Not printed | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 02/01/2027 → 12/06/2027 | 2025-08-15 | 2026-05-15 |
| Substations named | MUSKINGUM RIVER → MUSKINGUM | 2026-10-06 | Not reported |
| Substations named | MUSKINGUM → MUSKINGUM; MUSKINGUM RIVER | 2025-08-15 | 2026-05-15 |
| Substations named | MUSKINGUM; MUSKINGUM RIVER → MUSKINGUM RIVER | 2026-05-15 | 2026-10-06 |
| Substations named | MUSKINGUM → MUSKINGUM; MUSKINGUM RIVER | 2025-08-05 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 100 |
Muskingum River, OH | “Install a new 138kV breaker at Muskingum River 138kV on bus #1 to facilitate extension to customer site” 138kV |
| 2026-10-06 | TEAC Item 11 - AEP Supplemental Projects - Presentation p. 3 |
Muskingum River - Kammer 345 kV Line Section | No role wording 345 kV |
| 2026-10-06 | TEAC Item 11 - AEP Supplemental Projects - Presentation p. 7 |
Muskingum River 345kV Customer Delivery | “Install 2 - 345 kV 4000A 63kA circuit breakers and metering at Muskingum River 345kV station.” 345 kV |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 21 |
Muskingum River, OH | “Install a new 138kV breaker at Muskingum River 138kV on bus #1” 138kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.