Substation Scout

Eldean

Named in 4 PJM planning documents for 2 projects, from July 8, 2025 to May 8, 2026.

Existingdescribed as
DAYTONzone
—kV as printed
4mentions

Also printed as: Eldean Substation

PJM interconnection queue

A PJM queue substation page has the same name: Eldean (OH) — 3 queue requests filed, 0 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton-2022-003 Cancelled $13.5M 06/1/2024 Not printed 2026-02-13
SRRTEP Western
Dayton-2025-007 Conceptual $591.5M June 30th, 2032 1400 MW 2026-05-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
item 05 - Dayton Supplemental Projects p. 3
Dayton-2025-007 No role wording
2026-02-13 SRRTEP Western
Item 06 - Dayton Supplemental Projects p. 3
Dayton-2022-003 No role wording
2026-02-03 TEAC
Item 06 - Dayton Supplemental Projects p. 3
Dayton-2025-007 No role wording
2025-07-08 TEAC
Item 05 - Dayton Supplemental Projects p. 7
Dayton-2025-007 “vicinity of its Eldean Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this