Tri-State

Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
138kV, 345 kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Apple Grove, WV
AEP-2022-AP014 · s3143.1-.7
Conceptual $215.8M Phase 1 – 12/15/2025, Phase 2 – 12/15/2029 450 MW 2024-10-08
TEAC
Wayne County, WV
AEP-2022-AP032 · s3952.1-3
Conceptual $98.8 M 11/28/2029 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 64
Wayne County, WV No role wording
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 64
Wayne County, WV No role wording
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 36
Apple Grove, WV No role wording
345 kV
2026-05-15 SRRTEP Western
Item 01 - AEP Supplemental Projects p. 13
Wayne County, WV “Rebuild 2.26 mile single circuit 138kV line to replace the existing single circuit 138kV line between Tri-State and existing structure 160-16”
138kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 36
Apple Grove, WV No role wording
345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.