Bramah

Named in 6 PJM planning documents for 5 projects, from May 6, 2025 to July 7, 2026.

Newdescribed as
PECOzone
500 kVkV as printed
6mentions

Described as new: “new Bramah (North Delta) 500 kV substation” — source, page 15

Also printed as: Bramah substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah
b3737.50
Not printed Not printed 6/1/2029 Not printed 2026-05-08
TEAC
Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation
B4089.1 and B4089.2
Not printed $12M 10/14/2027 Not printed 2026-07-07
TEAC
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Not printed $12 million October 14, 2027 Not printed 2026-06-02
TEAC
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation Not printed $12M 10/14/2027 Not printed 2026-06-02
TEAC
PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 Not printed $12 million October 14, 2027 Not printed 2026-07-07
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$1.56M → $12M 2025-05-06 2025-05-06
Substations named BRAMAH; DELTA YORK; NORTH DELTA; PEACH BOTTOM → BRAMAH; CONASTONE; DELTA YORK; FURNACE RUN; PEACH BOTTOM 2025-05-06 2026-05-08

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1
PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 “energization and operation of the retained Bramah substation”
500 kV
2026-07-07 TEAC
Item 03 - 5034 Immediate Need Assessment - Second Read p. 5
Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation No role wording
500 kV
2026-06-02 TEAC
Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation “energize the Bramah substation”
500 kV
2026-06-02 TEAC
Item 09 - 5034 500 kV Line Cut-in Immediate Need Assessment - First Read p. 6
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation “energization of the Bramah substation”
500 kV
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 33
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah “Bring the Peach Bottom-Delta York 500 ‘5034’ kV line “in and out” of Bramah substation”
2025-05-06 TEAC
Item 10 - Reliability Analysis Update p. 15
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah “new Bramah (North Delta) 500 kV substation”
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this