Concord

Named in 1 PJM planning document for 1 project, on May 8, 2026.

Newdescribed as
DAYTONzone
138 kVkV as printed
1mentions

Described as new: “extend ~2-mile double circuit to a new 138 kV “Concord”” — source, page 4

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton-2025-007 Conceptual $591.5M June 30th, 2032 1400 MW 2026-05-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
item 05 - Dayton Supplemental Projects p. 4
Dayton-2025-007 “extend ~2-mile double circuit to a new 138 kV “Concord””
138 kV