Substation Scout

Peach Bottom

Named in 10 PJM planning documents for 7 projects, from February 4, 2025 to August 4, 2026.

Existingdescribed as
PECOzone
230 kV, 500 kV, 500kVkV as printed
10mentions

PJM interconnection queue

A PJM queue substation page has the same name: Peach Bottom (PA) — 11 queue requests filed, 8 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah
b3737.50
Not printed Not printed 6/1/2029 Not printed 2026-05-08
TEAC
Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation
B4089.1 and B4089.2
Not printed $12M 10/14/2027 Not printed 2026-07-07
TEAC
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Not printed $12 million October 14, 2027 Not printed 2026-06-02
TEAC
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation Not printed $12M 10/14/2027 Not printed 2026-06-02
TEAC
PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 Not printed $12 million October 14, 2027 Not printed 2026-07-07
TEAC
Peach Bottom Unit #2 Relay Replacement
PE-2024-007 · s3665.1
Not printed $836,000 11/3/2024 Not printed 2025-10-08
TEAC
Limerick
PE-2026-001
Engineering $2 million 12/21/2026 Not printed 2026-08-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$1.56M → $12M 2025-05-06 2025-05-06
Substations named BRAMAH; DELTA YORK; NORTH DELTA; PEACH BOTTOM → BRAMAH; CONASTONE; DELTA YORK; FURNACE RUN; PEACH BOTTOM 2025-05-06 2026-05-08
Substations named NEWLINVILLE → BRADFORD; MITTAL STEEL; NEWLINVILLE; PEACH BOTTOM 2026-01-06 2026-08-04

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PECO local plan submission for 2025 RTEP p. 9
Peach Bottom Unit #2 Relay Replacement “Upgraded Peach Bottom CB #225 relays and metering equipment”
2026-08-04 TEAC
Item 09 - PECO Supplemental Projects p. 7
Limerick No role wording
230 kV
2026-07-07 TEAC
Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1
PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 No role wording
500kV
2026-07-07 TEAC
Item 03 - 5034 Immediate Need Assessment - Second Read p. 5
Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation No role wording
500 kV
2026-06-02 TEAC
Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation No role wording
500 kV
2026-06-02 TEAC
Item 09 - 5034 500 kV Line Cut-in Immediate Need Assessment - First Read p. 6
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation No role wording
500 kV
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 33
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah No role wording
500 kV
2025-10-08 TEAC
Informational Only - PECO Local Plan Submission of the Supplemental Projects for 2025 p. 9
Peach Bottom Unit #2 Relay Replacement “Upgraded Peach Bottom CB #225 relays and metering equipment”
2025-05-06 TEAC
Item 10 - Reliability Analysis Update p. 15
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah No role wording
500 kV
2025-02-04 TEAC
Item 09 - PECO Supplemental Projects p. 4
Peach Bottom Unit #2 Relay Replacement “Upgraded Peach Bottom CB 215 & CB 225 relays”
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this