Peach Bottom
Named in 10 PJM planning documents for 7 projects, from February 4, 2025 to August 4, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Peach Bottom (PA) — 11 queue requests filed, 8 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| PECO Transmission Zone: Baseline b3737.50 –
Cut ‘5034’ 500 kV line in and out of Bramah b3737.50 |
Not printed | Not printed | 6/1/2029 | Not printed | 2026-05-08 TEAC |
| Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation B4089.1 and B4089.2 |
Not printed | $12M | 10/14/2027 | Not printed | 2026-07-07 TEAC |
| Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation | Not printed | $12 million | October 14, 2027 | Not printed | 2026-06-02 TEAC |
| PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation | Not printed | $12M | 10/14/2027 | Not printed | 2026-06-02 TEAC |
| PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 | Not printed | $12 million | October 14, 2027 | Not printed | 2026-07-07 TEAC |
| Peach Bottom Unit #2 Relay Replacement PE-2024-007 · s3665.1 |
Not printed | $836,000 | 11/3/2024 | Not printed | 2025-10-08 TEAC |
| Limerick PE-2026-001 |
Engineering | $2 million | 12/21/2026 | Not printed | 2026-08-04 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$1.56M → $12M | 2025-05-06 | 2025-05-06 |
| Substations named | BRAMAH; DELTA YORK; NORTH DELTA; PEACH BOTTOM → BRAMAH; CONASTONE; DELTA YORK; FURNACE RUN; PEACH BOTTOM | 2025-05-06 | 2026-05-08 |
| Substations named | NEWLINVILLE → BRADFORD; MITTAL STEEL; NEWLINVILLE; PEACH BOTTOM | 2026-01-06 | 2026-08-04 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic PECO local plan submission for 2025 RTEP p. 9 |
Peach Bottom Unit #2 Relay Replacement | “Upgraded Peach Bottom CB #225 relays and metering equipment” |
| 2026-08-04 | TEAC Item 09 - PECO Supplemental Projects p. 7 |
Limerick | No role wording 230 kV |
| 2026-07-07 | TEAC Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1 |
PECO Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation Immediate Need – July 7, 2026 | No role wording 500kV |
| 2026-07-07 | TEAC Item 03 - 5034 Immediate Need Assessment - Second Read p. 5 |
Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation | No role wording 500 kV |
| 2026-06-02 | TEAC Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1 |
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation | No role wording 500 kV |
| 2026-06-02 | TEAC Item 09 - 5034 500 kV Line Cut-in Immediate Need Assessment - First Read p. 6 |
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation | No role wording 500 kV |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 33 |
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah | No role wording 500 kV |
| 2025-10-08 | TEAC Informational Only - PECO Local Plan Submission of the Supplemental Projects for 2025 p. 9 |
Peach Bottom Unit #2 Relay Replacement | “Upgraded Peach Bottom CB #225 relays and metering equipment” |
| 2025-05-06 | TEAC Item 10 - Reliability Analysis Update p. 15 |
PECO Transmission Zone: Baseline b3737.50 – Cut ‘5034’ 500 kV line in and out of Bramah | No role wording 500 kV |
| 2025-02-04 | TEAC Item 09 - PECO Supplemental Projects p. 4 |
Peach Bottom Unit #2 Relay Replacement | “Upgraded Peach Bottom CB 215 & CB 225 relays” 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.