Hosensack
Named in 7 PJM planning documents for 4 projects, from March 18, 2026 to October 6, 2026.
Existingdescribed as
PPLzone
500kV, 69 kVkV as printed
10mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Hosensack 69kV Upgrade PPL-2026-0025 |
Conceptual | $3.4 M | 11/30/2028 | Not printed | 2026-10-06 TEAC |
| Hosensack, PA PPL-2026-0027 |
Conceptual | $4.9 M | 11/30/2029 | Not printed | 2026-05-08 TEAC |
| Milford Tap PPL-2026-0032 |
Conceptual | $1 M | 11/30/2030 | Not printed | 2026-08-13 SRRTEP Mid-Atlantic |
| Hosensack-Quarry 2 upgrade PPL-2026-0033 |
Conceptual | $3.6 M | 01/30/2028 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 5/1/2028 → 11/30/2028 | 2026-03-18 | 2026-05-14 |
| Substations named | MILFORD → HOSENSACK; MILFORD; SPRINGFIELD | 2026-05-14 | 2026-08-13 |
| In-service date | 11/30/2026 → 01/30/2028 | 2026-04-14 | 2026-05-14 |
| Substations named | SOUTH ALLENTOWN → HOSENSACK; QUARRY; SOUTH ALLENTOWN | 2026-04-14 | 2026-05-14 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 70 |
Hosensack 69kV Upgrade | “Upgrade the Hosensack 69kV yard to complete Double breaker-double bus design” 69 kV |
| 2026-10-06 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 75 |
Hosensack-Quarry 2 upgrade | No role wording |
| 2026-09-17* | SRRTEP Mid-Atlantic PPL local plan submission for 2026 RTEP p. 70 |
Hosensack 69kV Upgrade | “Upgrade the Hosensack 69kV yard to complete Double breaker-double bus
design” 69 kV |
| 2026-09-17* | SRRTEP Mid-Atlantic PPL local plan submission for 2026 RTEP p. 75 |
Hosensack-Quarry 2 upgrade | No role wording |
| 2026-08-13 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 12 |
Milford Tap | No role wording |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 13 |
Hosensack 69kV Upgrade | “Upgrade the Hosensack 69kV yard” 69 kV |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 18 |
Hosensack-Quarry 2 upgrade | No role wording |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 20 |
Hosensack, PA | “Upgrade the Hosensack 500kV Switchyard to a BAAH configuration” 500kV |
| 2026-04-07 | TEAC Item 05 - PPL Supplemental Projects p. 5 |
Hosensack, PA | “The current arrangement at Hosensack 500kV is built for BAAH but operated as a ring bus.” 500kV |
| 2026-03-18 | SRRTEP Mid-Atlantic Item 09 - PPL Supplemental Projects p. 12 |
Hosensack 69kV Upgrade | No role wording 69 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.