Callender Gap
Named in 7 PJM planning documents for 5 projects, from June 5, 2025 to October 6, 2026.
Newdescribed as
PPLzone
230kVkV as printed
11mentions
Described as new: “Install a four bay BAAH 230kV switchyard” — source, page 15
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Callender Gap, PA PPL-2025-0005 |
Conceptual | $73.5 M | 05/30/2028 | 500 MW | 2026-10-06 TEAC |
| Big Bass, PA PPL-2025-0012 |
Conceptual | $186.875 M | 05/30/2028 | 1,500 MW | 2026-10-06 TEAC |
| Lackawana, PA PPL-2025-0013 |
Conceptual | $74.9 M | 07/30/2028 | 1,400 MW | 2026-10-06 TEAC |
| Archbald Mountain, PA PPL-2025-0014 |
Conceptual | $220 M | 05/30/2028 | 1,000 MW | 2026-02-03 TEAC |
| Callender Gap, PA PPL-2026-0002 |
Conceptual | $76.5 M | 05/30/2029 | 1,200 MW | 2026-05-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 05/2027 → 05/30/2028 | 2025-05-06 | 2025-06-05 |
| Substations named | CALLENDER GAP; HOPATCONG; LACKAWANNA; PAUPACK → CALLENDER GAP; LACKAWANNA; PAUPACK | 2025-06-05 | 2026-10-06 |
| In-service date | 05/2027 → 05/30/2028 | 2025-07-08 | 2025-09-09 |
| In-service date | 07/2028 → 07/30/2028 | 2025-09-09 | 2025-10-08 |
| In-service date | 05/2027 → 05/30/2028 | 2025-09-09 | 2026-02-03 |
| In-service date | 5/2028 → 05/30/2029 | 2026-03-10 | 2026-05-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 15 |
Callender Gap, PA | “Install a four bay BAAH 230kV switchyard” 230kV |
| 2026-10-06 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 23 |
Lackawana, PA | No role wording |
| 2026-10-06 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 27 |
Big Bass, PA | No role wording |
| 2026-09-17* | SRRTEP Mid-Atlantic PPL local plan submission for 2026 RTEP p. 15 |
Callender Gap, PA | “Install a four bay BAAH 230kV switchyard” 230kV |
| 2026-09-17* | SRRTEP Mid-Atlantic PPL local plan submission for 2026 RTEP p. 23 |
Lackawana, PA | No role wording 230kV |
| 2026-09-17* | SRRTEP Mid-Atlantic PPL local plan submission for 2026 RTEP p. 27 |
Big Bass, PA | No role wording 230kV |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 10 |
Callender Gap, PA | “Install four new 230kV line terminals for the Customer lead lines at Callender Gap 230kV yard” 230kV |
| 2026-02-03 | TEAC Item 07 - PPL Supplemental Projects p. 7 |
Archbald Mountain, PA | “Install 230kV terminals for three 230kV lines” 230kV |
| 2025-10-08 | TEAC Item 09 - PPL Supplemental Projects p. 4 |
Lackawana, PA | No role wording 230kV |
| 2025-09-09 | TEAC Item 09 - PPL Supplemental Projects p. 10 |
Big Bass, PA | “Upgrade Lackawanna - Callender Gap 230kV Line” 230kV |
| 2025-06-05 | TEAC Item 05 - PPL Supplemental Projects p. 4 |
Callender Gap, PA | “Install a four bay BAAH 230kV switchyard” 230kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.