Petros

Named in 3 PJM planning documents for 1 project, from May 15, 2026 to October 6, 2026.

Newdescribed as
AEPzone
138 kVkV as printed
3mentions

Described as new: “Construct a greenfield breaker and a half station operated as a ring bus” — source, page 98

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
South Canton, OH/Torrey, OH
AEP-2025-OH007 · s4023.1-5
Engineering $49.124 M 10/13/2027 255 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 98
South Canton, OH/Torrey, OH “Construct a greenfield breaker and a half station operated as a ring bus”
138 kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 98
South Canton, OH/Torrey, OH “Construct a greenfield breaker and a half station operated as a ring bus”
138 kV
2026-05-15 SRRTEP Western
Item 01 - AEP Supplemental Projects p. 19
South Canton, OH/Torrey, OH “Construct a greenfield breaker and a half station operated as a ring bus with (4) 138 kV 3000A 63 kA circuit breakers.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.