Mayo Dunbar DP

Named in 2 PJM planning documents for 1 project, from September 18, 2025 to May 14, 2026.

Existingdescribed as
DOMzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
115 kV Mayo Dunbar DP Modification – EMC-EMC
DOM-2025-0022
Under construction $1.9M 5/31/2026 9.2 MW 2026-05-14
SRRTEP Southern

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named MAYO DUNBAR DP → BEECH BRANCH; COOL SPRINGS; MAYO DUNBAR DP 2025-09-18 2026-05-14
Substations named BEECH BRANCH; COOL SPRINGS; MAYO DUNBAR DP → BEECH BRANCH; COOL SPRINGS 2026-05-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-05-14 SRRTEP Southern
Item 04 - DOM Supplemental Projects p. 3
115 kV Mayo Dunbar DP Modification – EMC-EMC “move Mayo Dunbar DP station to the adjacent lot”
2025-09-18 SRRTEP Southern
Item 06 - DOM Supplemental Projects p. 4
115 kV Mayo Dunbar DP Modification – EMC-EMC “move Mayo Dunbar DP station to the adjacent lot”