Hope Creek

Named in 1 PJM planning document for 1 project, on May 8, 2026.

Not stateddescribed as
PJM system-widezone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
LS Power NJ SAA Baseline NJ Project Cancelations
b3737.37
Not printed Not printed 6/1/2029 Not printed 2026-05-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 30
LS Power NJ SAA Baseline NJ Project Cancelations No role wording