Lebanon

Named in 2 PJM planning documents for 2 projects, from May 8, 2026 to October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
2mentions

Also printed as: Lebanon substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Line #209 and Line #58 Partial Rebuild
DOM-2021-0006 · s2623
Engineering $66.89M 05/30/2029 46.6MW 2026-10-06
TEAC
Line #209 and Line #58 Partial Rebuild
DOM-2021-0006 Update · s2623
Engineering $66.89M 05/30/2029 46.6MW 2026-05-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$19.5M → $66.89M 2026-10-06 2026-10-06
Cost estimate
prior value printed on the same page
$19.5M → $66.89M 2026-05-08 2026-05-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 46
Line #209 and Line #58 Partial Rebuild No role wording
2026-05-08 TEAC
Item 09 - DOM Supplemental Projects p. 6
Line #209 and Line #58 Partial Rebuild No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.