Dixie Substation

Named in 4 PJM planning documents for 1 project, from January 16, 2026 to October 6, 2026.

Existingdescribed as
ATSIzone
69 kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dixie 69 kV Substation
ATSI-2026-005 · s3946.1
Not printed $3.43M 12/31/2027 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named DIXIE; OMNI; PERSTORP POLYOLS; TELEDYNE → DIXIE; OMNI; PERSTORP; PERSTORP POLYOLS; TELEDYNE 2026-01-16 2026-05-15
Substations named DIXIE; OMNI; PERSTORP; PERSTORP POLYOLS; TELEDYNE → DIXIE 2026-05-15 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 55
Dixie 69 kV Substation “At Dixie Substation, replace three 69 kV breakers”
69 kV
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 56
Dixie 69 kV Substation “At Dixie Substation, replace three 69 kV breakers”
69 kV
2026-05-15 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 12
Dixie 69 kV Substation “At Dixie Substation, replace three 69 kV breakers”
69 kV
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 7
Dixie 69 kV Substation “The existing Dixie Substation 69 kV breakers B6903, B6904 and B6923 are 60 years old”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this