Substation Scout

Shelby

Named in 2 PJM planning documents for 2 projects, from September 9, 2025 to May 8, 2026.

Existingdescribed as
DAYTONzone
138kV, 345 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton-2025-005 Conceptual $69.6M 6/2029 400 MW 2025-09-09
TEAC
Dayton-2025-007 Conceptual $591.5M June 30th, 2032 1400 MW 2026-05-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named SIDNEY → CREEKSIDE; MILLCREEK; SHELBY; SIDNEY 2025-07-08 2025-09-09

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
item 05 - Dayton Supplemental Projects p. 5
Dayton-2025-007 “Cutin the existing 345 kV transmission line from Miami to Shelby”
345 kV
2025-09-09 TEAC
Item 07 - Dayton Supplemental Projects p. 8
Dayton-2025-005 “Expand the existing Shelby substation”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this