Named in 2 PJM planning documents for 2 projects, from May 15, 2026 to July 17, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
2mentions

Also printed as: Ashtabula Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Ashtabula-Leroy Center 138 kV Q-1, Q-2, Q-3, and Q-4 lines
ATSI-2026-031
Not printed Not printed Not printed Not printed 2026-05-15
SRRTEP Western
Ashtabula - Leroy Center 138 kV Line
ATSI-2026-051
Not printed Not printed Not printed Not printed 2026-07-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 8
Ashtabula - Leroy Center 138 kV Line “Ashtabula Substation is operated in an abnormal configuration”
138 kV
2026-05-15 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 3
Ashtabula-Leroy Center 138 kV Q-1, Q-2, Q-3, and Q-4 lines No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.