Smithburg

Named in 2 PJM planning documents for 1 project, from February 4, 2025 to May 8, 2026.

Not stateddescribed as
PJM system-widezone
—kV as printed
2mentions

Also printed as: Smithburg substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
MAOD NJ SAA Baseline Project Cancelations
b3737.22
Not printed Not printed 12/31/2027 Not printed 2026-05-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$217.1M → $208.9M 2025-02-04 2025-02-04

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 26
MAOD NJ SAA Baseline Project Cancelations No role wording
2025-02-04 TEAC
Item 12 - Reliability Analysis Update p. 16
MAOD NJ SAA Baseline Project Cancelations No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.