Substation Scout

Windsor

Named in 2 PJM planning documents for 2 projects, from February 4, 2025 to May 8, 2026.

Existingdescribed as
PSEGzone
230 kVkV as printed
2mentions

Also printed as: Windsor Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PSEG Transmission Zone: NJ SAA Baseline Project Cancelations
b3737.40
Not printed Not printed 6/1/2029 Not printed 2026-05-08
TEAC
b3737.41 Cancellation: Windsor – Clarksville 230kV
b3737.41
Cancelled $1.49M Not printed Not printed 2025-02-04
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 31
PSEG Transmission Zone: NJ SAA Baseline Project Cancelations “Windsor Substation with double bundled 1590 ACSR conductor”
2025-02-04 TEAC
Item 12 - Reliability Analysis Update p. 10
b3737.41 Cancellation: Windsor – Clarksville 230kV “upgrading all terminal equipment at Windsor 230 kV”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this