Gordonsville
Named in 4 PJM planning documents for 4 projects, from May 6, 2025 to October 6, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Gordonsville (VA) — 2 queue requests filed, 0 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Dominion Transmission Zone: Baseline
230kV Line #2135 Hollymeade – Gordonsville b3800.300 & b3800.301 |
Not printed | $32.0 M | 6/1/2028 | Not printed | 2025-05-06 TEAC |
| Helm 230kV Delivery – DEV DOM-2018-0018 · s1841 |
Engineering | 14M | 06/01/2030 | 3.0 MW | 2026-10-06 TEAC |
| Do No Harm Analysis DOM-2025-0071-DNH |
Conceptual | $12M | 12/30/2028 | Not printed | 2026-01-06 TEAC |
| Do No Harm Analysis DOM-2025-0072 DNH · s3989.3 |
Conceptual | $115M | 03/01/2029 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$53.96 M → $32.0 M | 2025-05-06 | 2025-05-06 |
| Cost estimate prior value printed on the same page |
$7.5 → 14.0M | 2025-10-08 | 2025-10-08 |
| Cost estimate prior value printed on the same page |
$7.5 → 14M | 2026-10-06 | 2026-10-06 |
| In-service date | 12/30/2030 → 06/01/2030 | 2025-10-08 | 2026-10-06 |
| Substations named | HELM; LUCKY HILL → GORDONSVILLE; HELM; KYSER; LUCKY HILL; REMINGTON | 2025-10-08 | 2026-10-06 |
| Substations named | FOXBROOK LANE; FRANCES; GORDONSVILLE; N ANNA; NORTH ANNA; SOUTHALL → FRANCES; NORTH ANNA; SOUTHALL | 2026-01-06 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 25 |
Helm 230kV Delivery – DEV | No role wording |
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 93 |
Do No Harm Analysis | No role wording |
| 2026-03-10 | TEAC Item 09 - DOM Supplemental Projects p. 6 |
Do No Harm Analysis | “Gordonsville and Wesbey Drive substations” |
| 2026-01-06 | TEAC Item 07 - DOM Supplemental Projects p. 19 |
Do No Harm Analysis | No role wording 230 kV |
| 2025-05-06 | TEAC Item 10 - Reliability Analysis Update p. 6 |
Dominion Transmission Zone: Baseline 230kV Line #2135 Hollymeade – Gordonsville | No role wording |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.