East Springfield

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to January 16, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
3mentions

Also printed as: East Springfield station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection
ATSI-2024-044 · s3524.1
Not printed $2.47M 3/1/2025 200 MVA 2024-10-08
TEAC
East Springfield station
ATSI-2026-006
Not printed Not printed Not printed Not printed 2026-01-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $2.47M → $26.07M 2024-10-08 Not reported
In-service date 3/1/2025 → 11/1/2028 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 102
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection “Adjust relay settings at London, North Titus, and East Springfield Substations”
138 kV
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 8
East Springfield station “The East Springfield Substation has four 138 kV lines”
138 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 102
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection “Adjust relay settings at East Springfield and North Titus substations”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.