Substation Scout

Traynor

Named in 9 PJM planning documents for 7 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
JCPLzone
230 kV, 230-34.5 kV, 34.5 kVkV as printed
18mentions

Also printed as: Traynor Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Automatic Restoration Projects
JCPL-2023-029 · s3247.1
Not printed $1.92 12/31/2025 Not printed 2024-10-08
TEAC
Traynor – Whippany 230 kV Misoperation Relays
JCPL-2023-044 · s3253.1
Not printed $3.25M 11/15/2024 Not printed 2024-10-08
TEAC
Traynor No. 13 230-34.5kV Transformer
JCPL-2024-017 · s4013.1
Not printed $16.73M 05/24/2030 Not printed 2026-10-06
TEAC
Traynor No. 14 230-34.5kV Transformer
JCPL-2024-018 · s4014.1
Not printed $12.35M 12/20/2030 Not printed 2026-10-06
TEAC
Briant Park – Traynor 34.5 kV I35 Line Customer Connection
JCPL-2025-002 · s3760.1
Not printed $0.5 M 08/31/2025 5 MVA 2026-10-06
TEAC
Morris Court 34.5 kV Substation – Customer Connection
JCPL-2025-011 · s3964.1
Not printed $110,000 09/14/2026 10 MW 2026-10-06
TEAC
Valley View Substation
JCPL-2026-047
Not printed Not printed Not printed 16 MW 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named TRAYNOR; WHIPPANY SUBSTATIONS → TRAYNOR; WHIPPANY 2024-10-08 Not reported
Substations named TRAYNOR; WHIPPANY → TRAYNOR 2026-10-06 Not reported
Substations named TRAYNOR; WHIPPANY → TRAYNOR 2026-10-06 Not reported
Cost estimate $0.50 → $0.5 M 2025-06-12 2026-10-06
Substations named MORRIS COURT → BRIANT PARK; MORRIS COURT; TRAYNOR 2025-12-11 2026-01-15

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 15
Briant Park – Traynor 34.5 kV I35 Line Customer Connection “Modify relay settings at Briant Park and Traynor substations”
34.5 kV
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 27
Morris Court 34.5 kV Substation – Customer Connection “Upgrade remote terminal end relay settings at Briant Park and Traynor substations”
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 53
Traynor No. 13 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 13 230-34.5 kV Transformer”
230-34.5 kV
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 55
Traynor No. 14 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 14 230-34.5 kV Transformer”
230-34.5 kV
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 15
Briant Park – Traynor 34.5 kV I35 Line Customer Connection “Modify relay settings at Briant Park and Traynor substations.”
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 27
Morris Court 34.5 kV Substation – Customer Connection “Upgrade remote terminal end relay settings at Briant Park and Traynor substations”
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 53
Traynor No. 13 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 13 230-34.5 kV Transformer.”
230-34.5 kV
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 55
Traynor No. 14 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 14 230-34.5 kV Transformer.”
230-34.5 kV
2026-09-17 SRRTEP Mid-Atlantic
Item 01 - JCPL Supplemental Projects p. 10
Valley View Substation No role wording
34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 15
Automatic Restoration Projects “At Traynor, replace relaying”
34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 23
Traynor – Whippany 230 kV Misoperation Relays “Replace relaying and limiting substation conductor at Traynor and Whippany substations”
230 kV
2026-07-07 TEAC
Item 07 - JCPL Supplemental Projects p. 4
Traynor No. 13 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 13 230-34.5 kV Transformer.”
2026-07-07 TEAC
Item 07 - JCPL Supplemental Projects p. 6
Traynor No. 14 230-34.5kV Transformer “At Traynor Substation: Replace the Traynor No. 14 230-34.5 kV Transformer.”
2026-01-15 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 4
Morris Court 34.5 kV Substation – Customer Connection “Upgrade remote terminal end relay settings at Briant Park and Traynor substations”
2025-06-12 SRRTEP Mid-Atlantic
Item 01 - JCPL Supplemental Projects p. 3
Briant Park – Traynor 34.5 kV I35 Line Customer Connection “Modify relay settings at Briant Park and Traynor substations.”
34.5 kV
2025-03-13 SRRTEP Mid-Atlantic
Item 05 - JCPL Supplemental Projects p. 4
Briant Park – Traynor 34.5 kV I35 Line Customer Connection No role wording
34.5 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 15
Automatic Restoration Projects “At Traynor, replace relaying”
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 23
Traynor – Whippany 230 kV Misoperation Relays “Replace relaying and limiting substation conductor at Traynor and Whippany substations”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this