Teddy

Named in 1 PJM planning document for 1 project, on January 6, 2026.

Newdescribed as
AEPzone
765/345 kVkV as printed
1mentions

Described as new: “Construct a new 765/345KV greenfield substation interconnecting the new 765KV Marysville line” — source, page 48

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
West Cluster Recommended Selection (2nd Read)
b4068.1
Not printed $2,768.0M 10/1/2032 Not printed 2026-01-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 48
West Cluster Recommended Selection (2nd Read) “Construct a new 765/345KV greenfield substation interconnecting the new 765KV Marysville line”
765/345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.