502 Junction

Named in 2 PJM planning documents for 2 projects, from June 5, 2025 to January 6, 2026.

Existingdescribed as
PJM system-widezone
500 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary
b3800.102
Not printed $844.80M December 2028 Not printed 2026-01-06
TEAC
2024 W1 Regional Cluster Additional Scope
b4000.14
Not printed $3.0 M 12/31/2031 Not printed 2025-06-05
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$440.95M → $844.80M 2026-01-06 2026-01-06

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 66
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary “existing 502 Junction substation”
500 kV
2025-06-05 TEAC
Item 09 - Reliability Analysis Update p. 50
2024 W1 Regional Cluster Additional Scope No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.