Elm Farm Substation

Named in 3 PJM planning documents for 1 project, from January 6, 2026 to October 6, 2026.

Existingdescribed as
DOMzone
115/34.5 kV, 230 kVkV as printed
3mentions

Also printed as: Elm Farm

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer Load Request
DOM-2025-0031 · s4033
Engineering $1.3M 12/31/2027 69 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 82
Customer Load Request “install a second transformer (TX#2) at Elm Farm Substation”
115/34.5 kV
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 13
Customer Load Request “install a second transformer (TX#2) at Elm Farm Substation”
230 kV
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 4
Customer Load Request “install a second transformer (TX#2) at Elm Farm Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.