Kirk

Named in 2 PJM planning documents for 2 projects, on January 6, 2026.

Existingdescribed as
AEPzone
138 kV, 345 kVkV as printed
2mentions

PJM interconnection queue

A PJM queue substation page has the same name: Kirk (OH) — 3 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
West Cluster Recommended Selection (2nd Read)
b4068.1
Not printed $2,768.0M 10/1/2032 Not printed 2026-01-06
TEAC
Central/NW OH, Indiana.
AEP-2022-OH023, AEP-2022-OH034, AEP-2022-OH036, AEP-2022-OH045, AEP-2022-OH046, AEP-2022-OH075, AEP-2022-OH077, AEP-2023-OH016, AEP-2023-OH019, AEP-2023-OH032, AEP-2023-OH040, AEP-2023-OH044, AEP-2023-OH052, AEP-2023-OH063 · s3442.1-.30
Conceptual $378.3M 10/13/2027 968 MW 2026-09-08*
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 136
Central/NW OH, Indiana. “Perform remote end work at Innovation, Babbitt, and Kirk 138 kV stations”
138 kV
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 52
West Cluster Recommended Selection (2nd Read) “Rebuild 6.37 mile section of the double circuit West Millersport-Kirk 345kV circuit”
345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.