Gore

Named in 1 PJM planning document for 1 project, on January 6, 2026.

Not stateddescribed as
PJM system-widezone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary
b3800.102
Not printed $844.80M December 2028 Not printed 2026-01-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$440.95M → $844.80M 2026-01-06 2026-01-06

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 66
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.