YDC- West Tap

Named in 1 PJM planning document for 1 project, on January 16, 2026.

Not stateddescribed as
ATSIzone
69kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Cascade (Cedar Street) 69 kV Line
ATSI-2022-001 · s3495.1
Conceptual $34.7 M 3/31/2028 Not printed 2026-01-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CASCADE; CEDAR STREET → BLAIR STRIP STEEL; CASCADE; CEDAR ST; CEDAR STREET; HILLCREST; NEW WILMINGTON; PUBLIC WELFARE; RAY ST; WALMO; YDC WEST TAP 2024-10-08 2026-01-16

Every mention

DateDocumentProjectWhat the document says about it
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 17
Cascade (Cedar Street) 69 kV Line No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.