Woodside
Named in 4 PJM planning documents for 6 projects, from December 3, 2024 to January 6, 2026.
Newdescribed as
PJM system-widezone
500 kVkV as printed
6mentions
Described as new: “Woodside substation adjacent to existing Stonewall 138 kV substation” — source, page 66
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary b3800.102 |
Not printed | $844.80M | December 2028 | Not printed | 2026-01-06 TEAC |
| Recommended Solution: 2024-W1-708 b4000.1 |
Not printed | $1,945.05 M | 12/1/2029 | Not printed | 2025-01-07 TEAC |
| Recommended Solution: 2024-W1-551 b4000.13 |
Not printed | $13.97 M | 6/1/2032 | Not printed | 2025-01-07 TEAC |
| 2024 W1 Regional Cluster Additional Scope b4000.14 |
Not printed | $3.0 M | 12/31/2031 | Not printed | 2025-06-05 TEAC |
| 2024W1 – Regional Cluster Preferred Solution: 2024-W1-551 2024-W1-551 |
Not printed | $13.97 M | 12/1/2029 | Not printed | 2024-12-03 TEAC |
| 2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 2024-W1-708 |
Not printed | $1,944.98 M | 12/1/2029 | Not printed | 2024-12-03 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$440.95M → $844.80M | 2026-01-06 | 2026-01-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-01-06 | TEAC Item 09 - Reliability Analysis Update p. 66 |
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary | “Woodside substation adjacent to existing Stonewall 138 kV substation” 500 kV |
| 2025-06-05 | TEAC Item 09 - Reliability Analysis Update p. 50 |
2024 W1 Regional Cluster Additional Scope | No role wording |
| 2025-01-07 | TEAC Item 12 - Reliability Analysis Update p. 64 |
Recommended Solution: 2024-W1-708 | No role wording 500 kV |
| 2025-01-07 | TEAC Item 12 - Reliability Analysis Update p. 66 |
Recommended Solution: 2024-W1-551 | No role wording 500 kV |
| 2024-12-03 | TEAC Item 11 - Reliability Analysis Update p. 78 |
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 | No role wording 500 kV |
| 2024-12-03 | TEAC Item 11 - Reliability Analysis Update p. 79 |
2024W1 – Regional Cluster Preferred Solution: 2024-W1-551 | No role wording 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.