Substation Scout

Woodside

Named in 4 PJM planning documents for 6 projects, from December 3, 2024 to January 6, 2026.

Newdescribed as
PJM system-widezone
500 kVkV as printed
6mentions

Described as new: “Woodside substation adjacent to existing Stonewall 138 kV substation” — source, page 66

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary
b3800.102
Not printed $844.80M December 2028 Not printed 2026-01-06
TEAC
Recommended Solution: 2024-W1-708
b4000.1
Not printed $1,945.05 M 12/1/2029 Not printed 2025-01-07
TEAC
Recommended Solution: 2024-W1-551
b4000.13
Not printed $13.97 M 6/1/2032 Not printed 2025-01-07
TEAC
2024 W1 Regional Cluster Additional Scope
b4000.14
Not printed $3.0 M 12/31/2031 Not printed 2025-06-05
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-551
2024-W1-551
Not printed $13.97 M 12/1/2029 Not printed 2024-12-03
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708
2024-W1-708
Not printed $1,944.98 M 12/1/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$440.95M → $844.80M 2026-01-06 2026-01-06

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 66
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary “Woodside substation adjacent to existing Stonewall 138 kV substation”
500 kV
2025-06-05 TEAC
Item 09 - Reliability Analysis Update p. 50
2024 W1 Regional Cluster Additional Scope No role wording
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 64
Recommended Solution: 2024-W1-708 No role wording
500 kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 66
Recommended Solution: 2024-W1-551 No role wording
500 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 78
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 No role wording
500 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 79
2024W1 – Regional Cluster Preferred Solution: 2024-W1-551 No role wording
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this