Rockville

Named in 2 PJM planning documents for 1 project, from January 6, 2026 to October 6, 2026.

Not stateddescribed as
DOMzone
230kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
West Creek 230kV Delivery - DEV
DOM-2025-0054 · s3992
Conceptual $35M 7/26/2028 100 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 1/2/2029 → 07/26/2028 2025-10-08 2026-01-06
Substations named WEST CREEK → MIDLOTHIAN; NORTH POLE; ROCKVILLE; SHORT PUMP; WEST CREEK 2025-10-08 2026-01-06
Substations named MIDLOTHIAN; NORTH POLE; ROCKVILLE; SHORT PUMP; WEST CREEK → ROCKVILLE; SHORT PUMP; WEST CREEK 2026-01-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 85
West Creek 230kV Delivery - DEV No role wording
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 13
West Creek 230kV Delivery - DEV No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.