Substation Scout

Bermuda Hundred

Named in 8 PJM planning documents for 4 projects, from October 8, 2024 to October 6, 2026.

Newdescribed as
DOMzone
230kVkV as printed
11mentions

Described as new: “future Bermuda Hundred substation” — source, page 23

Also printed as: Bermuda Hundred Substation · Bermuda Hundred substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bermuda Hundred 230kV Delivery - DEV
DOM-2019-0021, DOM-2024-0022, DOM-2024-0023, DOM-2024-0024 - DNH
Conceptual 101.7M Q4 2030 Not printed 2026-07-07
TEAC
Do No Harm Analysis
DOM-2022-0062-DNH · s3862.2, s3862.3
Conceptual Not printed Q4 2031 Not printed 2026-10-06
TEAC
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2024-0018 · s3673
Engineering $20M Substation, $5M Transmission Line Q4 2027 255.0 MW 2025-10-08
TEAC
Sloan Drive 230kV Delivery - DEV
DOM-2024-0022 · s3510.1
Engineering $25.0 M Q4 2027 100 MW 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $101.7M → $15.0 M 2026-10-06 Not reported
Cost estimate $15.0 M → $92.7M 2024-10-08 2024-12-03
Cost estimate
prior value printed on the same page
$92.7M → $95.1M 2026-01-06 2026-01-06
Cost estimate $92.7M → $95.1M 2025-10-08 2026-01-06
Cost estimate
prior value printed on the same page
$95.1M → 101.7M 2026-07-07 2026-07-07
Cost estimate $95.1M → 101.7M 2026-01-06 2026-07-07
Cost estimate
prior value printed on the same page
$92.7M → $101.7M 2026-10-06 2026-10-06
In-service date Q4 2030 → Q4 2026 2026-10-06 Not reported
In-service date Q4 2026 → Q4 2028 2024-10-08 2024-12-03
In-service date Q4 2028 → Q4 2030 2026-01-06 2026-07-07
Status conceptual (Conceptual) → engineering (Engineering) 2026-10-06 Not reported
Status engineering (Engineering) → conceptual (Conceptual) 2026-01-06 2026-07-07
Substations named ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ALLIED; BERMUDA HUNDRED; ICI 2026-10-06 Not reported
Substations named ALLIED; BERMUDA HUNDRED; ICI → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-10-08 2024-12-03
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS → ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-12-03 2025-10-08
Substations named ENON; MEADOWVILLE; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2025-10-08 2026-01-06
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-01-06 2026-07-07
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-07-07 2026-10-06
In-service date Q4 2027 → 12/01/2030 2025-01-07 2025-05-06
In-service date 12/01/2030 → Q4 2027 2025-05-06 2025-10-08
Status engineering (Engineering) → conceptual (Conceptual) 2025-01-07 2025-05-06
Status conceptual (Conceptual) → engineering (Engineering) 2025-05-06 2025-10-08
Substations named CHICKAHOMINY; ELMONT; THICKET; WHITE OAK → BERMUDA HUNDRED; CHICKAHOMINY; DARBYTOWN; ELKO; ELMONT; TECHPARK PLACE; THICKET; WHITE OAK 2025-01-07 2025-05-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 109
Do No Harm Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 159
Bermuda Hundred 230kV Delivery - DEV “new substation (Bermuda Hundred)”
230kV
2026-09-08* SRRTEP Southern
Dominion p. 182
Sloan Drive 230kV Delivery - DEV No role wording
230kV
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 16
Bermuda Hundred 230kV Delivery - DEV “future Bermuda Hundred substation”
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 5
Do No Harm Analysis No role wording
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 23
Bermuda Hundred 230kV Delivery - DEV “future Bermuda Hundred substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 56
Dominion Transmission Zone: Supplemental Do No Harm Analysis “future Bermuda Hundred”
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 7
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 19
Bermuda Hundred 230kV Delivery - DEV “future Bermuda Hundred substation”
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 159
Bermuda Hundred 230kV Delivery - DEV “new substation (Bermuda Hundred)”
230kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 182
Sloan Drive 230kV Delivery - DEV “extending a new 230kV feed from future Bermuda Hundred Substation”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.