Named in 1 PJM planning document for 1 project, on January 6, 2026.

Not stateddescribed as
DOMzone
115 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
DOM-2025-0073 Not printed Not printed Not printed Not printed 2026-01-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 8
DOM-2025-0073 No role wording
115 kV