Frances

Named in 2 PJM planning documents for 2 projects, from January 6, 2026 to October 6, 2026.

Newdescribed as
DOMzone
230 kVkV as printed
4mentions

Described as new: “new 230 kV delivery point (Frances)” — source, page 61

Also printed as: Frances Sub · Frances substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Frances 230kV Delivery - REC
DOM-2025-0071 · s3997
Conceptual $21M 8/01/2027 176 MW 2026-10-06
TEAC
Do No Harm Analysis
DOM-2025-0071-DNH · s3997.3, s3997.4
Conceptual $12M 12/30/2028 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named FOXBROOK LANE; FRANCES; GORDONSVILLE; N ANNA; NORTH ANNA; SOUTHALL → FRANCES; NORTH ANNA; SOUTHALL 2026-01-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 61
Frances 230kV Delivery - REC “new 230 kV delivery point (Frances)”
230 kV
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 64
Do No Harm Analysis “Install associated 230 kV terminal equipment at Frances and North Anna”
230 kV
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 16
Frances 230kV Delivery - REC “Connect a new Frances substation”
230 kV
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 19
Do No Harm Analysis “Install associated 230 kV terminal equipment at Frances and North Anna”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.