Substation Scout

Doubs

Named in 4 PJM planning documents for 8 projects, from December 3, 2024 to January 6, 2026.

Existingdescribed as
PJM system-widezone
500 kV, 500.kV, 500/230 kVkV as printed
8mentions

Also printed as: DOUBS · Doubs Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Brandon Shores Deactivation Project Updates: Summary of Cost Changes
b3780.1
Not printed 1513.96 12/31/2028 Not printed 2025-02-04
TEAC
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary
b3800.102
Not printed $844.80M December 2028 Not printed 2026-01-06
TEAC
Recommended Solution: 2024-W1-708
b4000.1
Not printed $1,945.05 M 12/1/2029 Not printed 2025-01-07
TEAC
PJM Selected Solution: Breaker Upgrades
b4000.110
Not printed $100.85 M 6/1/2029 Not printed 2025-01-07
TEAC
Recommended Solution: 2024-W1-551
b4000.13
Not printed $13.97 M 6/1/2032 Not printed 2025-01-07
TEAC
2024W1 – Regional Cluster Preferred Solution: Breaker Upgrades Not printed $88.09 M 6/1/2029 Not printed 2024-12-03
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-551
2024-W1-551
Not printed $13.97 M 12/1/2029 Not printed 2024-12-03
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708
2024-W1-708
Not printed $1,944.98 M 12/1/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
738.83 → 1513.96 2025-02-04 2025-02-04
Cost estimate
prior value printed on the same page
$440.95M → $844.80M 2026-01-06 2026-01-06
Cost estimate $100.85 M → $10.06 M 2025-01-07 2025-04-01
Cost estimate
prior value printed on the same page
$11.5 M → $10.06 M 2025-04-01 2025-04-01
Substations named ASHBURN; BEAUMEADE; BRADDOCK; BRAMBLETON; BRISTERS; BULL RUN; BUTTERMILK; CABIN RUN; CARSON; CLIFTON; DOUBS; EVERGREEN MILLS; GOOSE CREEK; LADYSMITH; LIBERTY; LOCKRIDGE; LOUDOUN; MARSH RUN; MORRISVILLE; MOSBY; MT STORM; NIMBUS; NIVO 1; NORTH ANNA; PARAGON PARK; PLEASANTVIEW; REMINGTON; ROUNDTABLE; VINT HILL; YARDLEY → DOUBS 2025-01-07 2025-04-01

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 66
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary No role wording
2025-02-04 TEAC
Item 12 - Reliability Analysis Update p. 13
Brandon Shores Deactivation Project Updates: Summary of Cost Changes “Replace line drops to Doubs transformer 3”
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 65
Recommended Solution: 2024-W1-708 “Upgrade the terminal equipment on the Doubs No. 1 500/230 kV Transformer”
500/230 kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 66
Recommended Solution: 2024-W1-551 “Terminate the Woodside - Goose Creek 500 kV Line into Doubs Substation”
500 kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 80
PJM Selected Solution: Breaker Upgrades No role wording
500.kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 78
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 “Upgrade the terminal equipment on the Doubs No. 1 500/230 kV Transformer”
500/230 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 79
2024W1 – Regional Cluster Preferred Solution: 2024-W1-551 “Terminate the Woodside - Goose Creek 500 kV Line into Doubs Substation”
500 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 91
2024W1 – Regional Cluster Preferred Solution: Breaker Upgrades No role wording
500.kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this