Joffre Substation

Named in 2 PJM planning documents for 1 project, from January 16, 2026 to August 14, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Joffre 138 kV Substation
APS-2026-003
Conceptual $0.05 M 12/10/2027 Not printed 2026-08-14
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 05/27/2027 → 12/10/2027 2026-01-16 2026-08-14

Every mention

DateDocumentProjectWhat the document says about it
2026-08-14 SRRTEP Western
Item 01 - APS Supplemental Projects p. 7
Joffre 138 kV Substation “existing Joffre Substation”
138 kV
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 5
Joffre 138 kV Substation “near the existing Joffre Substation”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this