Rocky Point

Named in 1 PJM planning document for 1 project, on January 6, 2026.

Existingdescribed as
PEPCOzone
500 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Exelon/PEPCO Cluster
b4052.1
Not printed $282.16 M 6/1/2032 Not printed 2026-01-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 25
Exelon/PEPCO Cluster “Rocky Point 500 kV remote work for Dickerson (new 500 kV) - Rocky Point line”
500 kV