West Creek

Named in 3 PJM planning documents for 1 project, from October 8, 2025 to October 6, 2026.

Newdescribed as
DOMzone
230kVkV as printed
3mentions

Described as new: “new substation (West Creek)” — source, page 84

Also printed as: West Creek Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0054 · s3992
Conceptual $35M 7/26/2028 100 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 1/2/2029 → 07/26/2028 2025-10-08 2026-01-06
Substations named WEST CREEK → MIDLOTHIAN; NORTH POLE; ROCKVILLE; SHORT PUMP; WEST CREEK 2025-10-08 2026-01-06
Substations named MIDLOTHIAN; NORTH POLE; ROCKVILLE; SHORT PUMP; WEST CREEK → ROCKVILLE; SHORT PUMP; WEST CREEK 2026-01-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 84
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (West Creek)”
230kV
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (West Creek)”
230kV
2025-10-08 TEAC
Item 12 - DOM Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (West Creek)”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this