Substation Scout

Meadowville

Named in 6 PJM planning documents for 4 projects, from December 3, 2024 to October 6, 2026.

Newdescribed as
DOMzone
230kVkV as printed
10mentions

Described as new: “addition of Meadowville substation” — source, page 9

Also printed as: Meadowville substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer Load Request
DOM-2019-0021, DOM-2024-0022, DOM-2024-0023, DOM-2024-0024 – DNH · s3672
Conceptual $101.7M Q4 2030 Not printed 2026-10-06
TEAC
Meadowville 230kV Delivery - DEV
DOM-2024-0023 · s3671
Engineering $36.9M Q1 2028 300.0 MW 2025-10-08
TEAC
Do No Harm Analysis
DOM-2024-0023 - DNH · s3671
Conceptual Lines 211 and 228: $33M Line 238: $112M Q4 2030 300MW 2025-10-08
TEAC
White Mountain 230kV Delivery - DEV
DOM-2024-0024
Engineering $19.0M Q1 2028 100.0 MW 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $101.7M → $15.0 M 2026-10-06 Not reported
Cost estimate $15.0 M → $92.7M 2024-10-08 2024-12-03
Cost estimate
prior value printed on the same page
$92.7M → $95.1M 2026-01-06 2026-01-06
Cost estimate $92.7M → $95.1M 2025-10-08 2026-01-06
Cost estimate
prior value printed on the same page
$95.1M → 101.7M 2026-07-07 2026-07-07
Cost estimate $95.1M → 101.7M 2026-01-06 2026-07-07
Cost estimate
prior value printed on the same page
$92.7M → $101.7M 2026-10-06 2026-10-06
In-service date Q4 2030 → Q4 2026 2026-10-06 Not reported
In-service date Q4 2026 → Q4 2028 2024-10-08 2024-12-03
In-service date Q4 2028 → Q4 2030 2026-01-06 2026-07-07
Status conceptual (Conceptual) → engineering (Engineering) 2026-10-06 Not reported
Status engineering (Engineering) → conceptual (Conceptual) 2026-01-06 2026-07-07
Substations named ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ALLIED; BERMUDA HUNDRED; ICI 2026-10-06 Not reported
Substations named ALLIED; BERMUDA HUNDRED; ICI → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-10-08 2024-12-03
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS → ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-12-03 2025-10-08
Substations named ENON; MEADOWVILLE; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2025-10-08 2026-01-06
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-01-06 2026-07-07
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-07-07 2026-10-06
Substations named MEADOWVILLE; SLOAN DRIVE; WHITE MOUNTAIN → SLOAN DRIVE; WHITE MOUNTAIN 2024-12-03 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 49
Customer Load Request “Connect future Meadowville substation”
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 16
Customer Load Request “Connect future Meadowville substation”
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 23
Customer Load Request “Connect future Meadowville substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 16
Meadowville 230kV Delivery - DEV “new substation (Meadowville)”
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 21
Customer Load Request “future Meadowville substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 58
Do No Harm Analysis No role wording
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 9
Do No Harm Analysis “addition of Meadowville substation”
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 14
Meadowville 230kV Delivery - DEV “DEV Distribution has submitted a DP Request for a new substation (Meadowville)”
230kV
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 17
White Mountain 230kV Delivery - DEV “adjacent to future Meadowville Substation”
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 19
Customer Load Request “Connect future Meadowville substation”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.