Dale

Named in 6 PJM planning documents for 5 projects, from October 8, 2024 to January 16, 2026.

Existingdescribed as
ATSIzone
138 kV, 69 kVkV as printed
10mentions

Also printed as: Dale Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gilchrist – Star 69 kV Line
ATSI-2022-028 (s3359.1) · s3359.1
Not printed $71.7 M 12/1/2027 Not printed 2025-10-08
TEAC
Glenmount 138 kV Substation
ATSI-2023-009 · s3546.1
Not printed $23.54 M 12/31/2027 55 MW 2025-10-08
TEAC
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line
ATSI-2023-012 · s3498.1
Not printed $5.4M 6/19/2028 Not printed 2024-10-08
TEAC
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line Customer Connection
ATSI-2024-023 · s3453.1
Not printed $0.63 M 2/7/2025 21 MVA 2024-10-08
TEAC
Dale 138 kV Substation
ATSI-2026-004
Not printed Not printed Not printed 56 MW 2026-01-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $71.7 M → $62.5 M 2025-10-08 Not reported
Cost estimate $62.5 M → $71.7 M Not reported Not reported
Cost estimate
prior value printed on the same page
$97.7 M → $71.7 M Not reported Not reported
Cost estimate $62.5 M → $71.7 M 2024-10-08 2024-10-18
Cost estimate
prior value printed on the same page
$97.7 M → $71.7 M 2024-10-18 2024-10-18
Cost estimate
prior value printed on the same page
$97.7 M → $71.7 M 2025-10-08 2025-10-08
Substations named DALE; GILCHRIST; MARTIN; MCKNIGHTS; PORTAGE LAKES; STAR → DALE; GILCHRIST; MARTIN; STAR 2024-10-18 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 74
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line No role wording
69 kV
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 80
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line Customer Connection “Revise relay settings at Cloverdale and Dale substations”
69 kV
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 12
Glenmount 138 kV Substation No role wording
138 kV
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 16
Gilchrist – Star 69 kV Line No role wording
69 kV
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 6
Dale 138 kV Substation “The 138 kV yard at Dale Substation is currently configured as a straight bus”
138 kV
2025-10-08 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 12
Glenmount 138 kV Substation No role wording
138 kV
2025-10-08 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 17
Gilchrist – Star 69 kV Line No role wording
69 kV
2024-10-18 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 8
Gilchrist – Star 69 kV Line No role wording
69 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 74
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line No role wording
69 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 80
ATSI Transmission Zone M-3 Process Cloverdale – Dale No. 2 69 kV Line Customer Connection “Revise relay settings at Cloverdale and Dale substations”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.