North Titus

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to January 16, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection
ATSI-2024-044 · s3524.1
Not printed $2.47M 3/1/2025 200 MVA 2024-10-08
TEAC
East Springfield station
ATSI-2026-006
Not printed Not printed Not printed Not printed 2026-01-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $2.47M → $26.07M 2024-10-08 Not reported
In-service date 3/1/2025 → 11/1/2028 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 102
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection “Adjust relay settings at London, North Titus, and East Springfield Substations”
138 kV
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 8
East Springfield station No role wording
138 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 102
ATSI Transmission Zone M-3 Process East Springfield 138 kV Customer Connection “Adjust relay settings at East Springfield and North Titus substations”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.