Burches Hill

Named in 1 PJM planning document for 1 project, on January 6, 2026.

Existingdescribed as
DOMzone
500 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Regional Solution: 2025-W1-275 Portfolio
b4053.1
Not printed $4832.45 6/1/2032 Not printed 2026-01-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 39
Regional Solution: 2025-W1-275 Portfolio “Uprate terminal equipment at Burches Hill substation so as not to limit the conductor rating.”
500 kV