Substation Scout

Hanging Rock

Named in 2 PJM planning documents for 2 projects, from August 5, 2025 to July 7, 2026.

Existingdescribed as
AEPzone
—kV as printed
2mentions

PJM interconnection queue

A PJM queue substation page has the same name: Hanging Rock (OH) — 5 queue requests filed, 3 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hanging Rock, OH
AEP-2025-OH014
Not printed Not printed 05/01/2029 1000MW 2025-08-05
TEAC
Hanging Rock, OH/Baker, KY
AEP-2026-AP007
Not printed Not printed Not printed 1000 MW 2026-07-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Item 10 - AEP Supplemental Projects p. 3
Hanging Rock, OH/Baker, KY No role wording
2025-08-05 TEAC
Item 07 - AEP Supplemental Projects p. 3
Hanging Rock, OH “existing Hanging Rock station”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this