Pleasant View
Named in 4 PJM planning documents for 5 projects, from October 8, 2024 to September 8, 2026.
Existingdescribed as
DOMzone
230 kV, 230kV, 500-230kVkV as printed
10mentions
Also printed as: Pleasant View Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Do No Harm Analysis DOM-2021-0016-DNH · s2609.2 |
In service | $40.0 M | 12/15/2023 | Not printed | 2024-10-08 TEAC |
| Pleasant View - Add 4th TX - DEV DOM-2022-0010 · s3029 |
Engineering | $1.0 M | 03/06/2025 | 55.0 MW | 2024-10-08 TEAC |
| Twin Creeks 230kV Delivery - DEV DOM-2022-0043 · s3049 |
Engineering | $20.0 M | 12/31/2024 | 100MW | 2024-10-08 TEAC |
| Pluto 230kV Delivery - DEV DOM-2022-0056 · s3080 |
Engineering | $20.0 M | 06/01/2026 | 100MW | 2024-10-08 TEAC |
| Dominion Transmission Zone: Supplemental
Equipment Material Condition, Performance Risk DOM-2026-0016 |
Conceptual | Not printed | Not printed | Not printed | 2026-09-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08 | TEAC Item 10 - DOM Supplemental Projects p. 6 |
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance Risk | “Replace the 230 kV cap banks at Liberty, Clifton, Greenwich, Lanexa, Pleasant View, Jefferson Street, Valley and Newport News” 230 kV |
| 2026-09-08* | SRRTEP Southern Dominion p. 100 |
Pluto 230kV Delivery - DEV | No role wording |
| 2026-09-08* | SRRTEP Southern Dominion p. 17 |
Do No Harm Analysis | “Upgrade 230kV Pleasant View breakers” 230kV |
| 2026-09-08* | SRRTEP Southern Dominion p. 23 |
Pleasant View - Add 4th TX - DEV | “feed the new transformer at Pleasant View” |
| 2026-09-08* | SRRTEP Southern Dominion p. 79 |
Twin Creeks 230kV Delivery - DEV | No role wording |
| 2026-04-07 | TEAC Item 09 - DOM Supplemental Projects p. 5 |
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance Risk | “The 230 kV cap banks needing replacement between 2027 and 2028 are located at Pleasant View” 230 kV |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 100 |
Pluto 230kV Delivery - DEV | No role wording |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 22 |
Pleasant View - Add 4th TX - DEV | “add the 4th distribution transformer at Pleasant View Substation” |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 79 |
Twin Creeks 230kV Delivery - DEV | No role wording |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 9 |
Do No Harm Analysis | “Upgrade 230kV Pleasant View breakers L3T203 and L3T2180” 500-230kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.