Substation Scout

Cleveland

Named in 3 PJM planning documents for 1 project, from July 17, 2025 to October 6, 2026.

Existingdescribed as
PPLzone
69kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mount Carmel, PA
PPL-2025-0011
Conceptual $0.9 M 12/10/2026 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CLEVELAND; ELDRED → BLASCHAK; CLEVELAND; ELDRED 2026-10-06 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 7
Mount Carmel, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 7
Mount Carmel, PA “existing Eldred - Cleveland 69kV line”
69kV
2025-07-17 SRRTEP Mid-Atlantic
Item 01 - PPL Supplemental Projects p. 6
Mount Carmel, PA “existing Eldred - Cleveland 69kV line”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.