Named in 4 PJM planning documents for 1 project, from June 5, 2025 to October 6, 2026.

Not stateddescribed as
PPLzone
138kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Orefield, PA
PPL-2025-0006
Conceptual $194 M 05/31/2028 1000 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $159 M → $194 M 2025-06-05 2025-11-04
In-service date 10/2026 → 05/30/2028 2025-05-06 2025-06-05
In-service date 05/30/2028 → 05/31/2028 2025-06-05 2025-11-04
Substations named ALBURTIS; ALLENTOWN; OREFIELD; SIEGFRIED; SUSQUEHANNA; WESCOSVILLE → ALLENTOWN; OREFIELD; SIEGFRIED; SUSQUEHANNA; WESCOSVILLE 2025-11-04 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 17
Orefield, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 17
Orefield, PA No role wording
138kV
2025-11-04 TEAC
Item 08 - PPL Supplemental Projects p. 4
Orefield, PA No role wording
138kV
2025-06-05 TEAC
Item 05 - PPL Supplemental Projects p. 6
Orefield, PA No role wording
138kV