Substation Scout

Trainer

Named in 4 PJM planning documents for 4 projects, from October 8, 2025 to October 6, 2026.

Existingdescribed as
PECOzone
230 kV, 230kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Chichester Relay Upgrade
b3942.1
Not printed $0.691M 06-01-2030 Not printed 2025-11-04
TEAC
Chichester Relay Upgrade Not printed $0.031M 06-01-2030 Not printed 2025-10-08
TEAC
Navy Yard-Richmond New 230kV Line
PE-2025-008
Engineering Not printed Phase 1 – 12/31/2029, Phase 2 – 6/1/2031 500 MW 2026-04-07
TEAC
PE-2026-014 Not printed Not printed Not printed Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 15 - PECO Supplemental Projects - Presentation p. 3
PE-2026-014 “Trainer 230kV circuit breakers 785 and 875 are oil filled breakers installed in 1973 and 1983 (respectively) and are in deteriorating condition”
230kV
2026-04-07 TEAC
Item 08 - PECO Supplemental Projects p. 15
Navy Yard-Richmond New 230kV Line “Replace Trainer 230 kV circuit breaker #785, relays, equipment CTs.”
230 kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 15
Chichester Relay Upgrade No role wording
230 kV
2025-10-08 TEAC
Item 13 - Reliability Analysis Update p. 15
Chichester Relay Upgrade No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this