Named in 1 PJM planning document for 1 project, on December 1, 2026.

Newdescribed as
AEPzone
765/345 kVkV as printed
1mentions

Described as new. The quoted wording calls this substation new. “Construct a new 765/345 kV station (Manilla Ridge)” — source, page 24

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Project Avalon
AEP-2026-AP005
Conceptual $224.906 M 09/01/2029 1200 MW 2026-12-01
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 9/2029 → 09/01/2029 2026-05-08 2026-12-01

Every mention

DateDocumentProjectWhat the document says about it
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 24
Project Avalon “Construct a new 765/345 kV station (Manilla Ridge)”
765/345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.