Enlow
Named in 4 PJM planning documents for 2 projects, from December 13, 2024 to October 6, 2026.
Existingdescribed as
APSzone
138 kVkV as printed
4mentions
Also printed as: Enlow Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Misoperation Relay Projects APS-2024-098 to 105, APS-2024-111 to 114, APS-2024-116, APS-2024-118 |
Not printed | Not printed | Not printed | Not printed | 2024-12-13 SRRTEP Western |
| Misoperation Relays: Cecil – Enlow 138 kV Line APS-2024-105 · s3867.1 |
Not printed | $4.0M | 06/11/2029 | Not printed | 2026-10-06 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 33 |
Misoperation Relays: Cecil – Enlow 138 kV Line | “At Enlow Substation, replace circuit breaker, disconnect switches, line trap, line tuner and coax, CVT and relaying.” 138 kV |
| 2026-09-28* | SRRTEP Western APS local plan submission of the supplemental projects for 2026 RTEP p. 33 |
Misoperation Relays: Cecil – Enlow 138 kV Line | “At Enlow Substation, replace circuit breaker” |
| 2025-10-17 | SRRTEP Western Item 02 - APS Supplemental Projects p. 12 |
Misoperation Relays: Cecil – Enlow 138 kV Line | “At Enlow Substation, replace circuit breaker” 138 kV |
| 2024-12-13 | SRRTEP Western Item 15 - APS Supplemental Project p. 6 |
Misoperation Relay Projects | No role wording 138 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.