Substation Scout

Palmer 1 & 2 (CUSTOMER)

Named in 1 PJM planning document for 1 project, on December 1, 2026.

Not stateddescribed as
AEPzone
345kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements
AEP-2024-IM014, AEP-2025-OH016, AEP-2025-OH017, AEP-2025-OH018, AEP-2025-OH019
Conceptual $607.548 M 09/26/2031 1,300 MW 2026-12-01
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ALLEN; EAST LIMA; RP MONE; SORENSON → BOSC 1A 1B CUSTOMER; BOSC 2A 2B CUSTOMER; EAST LIMA; EBERSOLE; FLAG CITY; FOSTORIA CENTRAL; HILLCREST; LYKA; MADDOX CREEK; NORSE; NORTH FINDLAY; PALMER 1 2 CUSTOMER; PEONY 1 2 CUSTOMER; PYRITE; SAIDIN; SORENSON; VALOR 1 2 CUSTOMER; WAYNE TRACE; WAYNEDALE 2024-11-06 2026-12-01

Every mention

DateDocumentProjectWhat the document says about it
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 34
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this